Wellington Airport Southern Seawall Renewal
The Southern Seawall Renewal will rebuild about 400 metres of the seawall that protects the southern end of Wellington Airport's runway from Cook Strait swells and storms. The original seawalls date from 1954 and are reaching the end of their life. A new wall of large concrete armour units and rock will be laid over the old one, and an unprotected, eroding bank to the east will also be armoured. The project includes two new kororā (little penguin) colonies with nest boxes, planting and fencing. It was the first project in the Wellington region to gain fast-track consent, in May 2026. Enabling works are expected to start in 2026, with main seawall construction planned from around 2029 into the early 2030s.
Timeline
Oct 2025
Wellington Airport applied for fast-track consent.
2026
Enabling works are expected to begin in 2026.
15 May 2026
The project was granted fast-track approval, the first in the Wellington region.
2029
Main seawall construction is planned to start in the airport's 2029 to 2034 capital period, subject to airline consultation.
Project team
- Client / DeveloperUnclaimedClaim this role →
- Project ManagerUnclaimedClaim this role →
- Quantity SurveyorUnclaimedClaim this role →
- ArchitectUnclaimedClaim this role →
- Structural EngineerUnclaimedClaim this role →
- Building Services EngineerUnclaimedClaim this role →
- Civil EngineerUnclaimedClaim this role →
- Fire EngineerUnclaimedClaim this role →
Build team
- Main ContractorUnclaimedClaim this role →
- Mechanical ContractorUnclaimedClaim this role →
- Electrical ContractorUnclaimedClaim this role →
- Steel FabricatorUnclaimedClaim this role →
- Concrete ContractorUnclaimedClaim this role →
- PlumberUnclaimedClaim this role →
Products used
Drag to scroll