Wellington Airport Southern Seawall Renewal

Have a better image?

The Southern Seawall Renewal will rebuild about 400 metres of the seawall that protects the southern end of Wellington Airport's runway from Cook Strait swells and storms. The original seawalls date from 1954 and are reaching the end of their life. A new wall of large concrete armour units and rock will be laid over the old one, and an unprotected, eroding bank to the east will also be armoured. The project includes two new kororā (little penguin) colonies with nest boxes, planting and fencing. It was the first project in the Wellington region to gain fast-track consent, in May 2026. Enabling works are expected to start in 2026, with main seawall construction planned from around 2029 into the early 2030s.

Timeline

  1. Oct 2025

    Wellington Airport applied for fast-track consent.

  2. 2026

    Enabling works are expected to begin in 2026.

  3. 15 May 2026

    The project was granted fast-track approval, the first in the Wellington region.

  4. 2029

    Main seawall construction is planned to start in the airport's 2029 to 2034 capital period, subject to airline consultation.

Products used

Drag to scroll