Waiwera Thermal Springs Redevelopment
The project will bring back the Waiwera hot springs on the Hibiscus Coast, about 40 kilometres north of central Auckland. The site was first developed as a spa in 1875, but the water park closed in 2018 and sat empty for years before demolition began in 2023. The 1.7 hectare site will become a bathing and wellness destination with close to 30 thermal pools at different temperatures, saunas, cold plunges, bush bathing trails, spa treatments and dining, along with family areas and adults-only zones. Auckland Council granted resource consent in 2026. Construction is expected to begin in early 2027, with opening planned for mid-2028.
Timeline
2018
The former Waiwera water park closed.
2023
Demolition of the old facilities began.
1 Sep 2026
Auckland Council granted resource consent for the redevelopment.
2027
Construction is expected to begin in early 2027.
2028
Opening is planned for mid-2028.
Project team
- Client / DeveloperUnclaimedClaim this role →
- Project ManagerUnclaimedClaim this role →
- Quantity SurveyorUnclaimedClaim this role →
- ArchitectUnclaimedClaim this role →
- Structural EngineerUnclaimedClaim this role →
- Building Services EngineerUnclaimedClaim this role →
- Civil EngineerUnclaimedClaim this role →
- Fire EngineerUnclaimedClaim this role →
Build team
- Main ContractorUnclaimedClaim this role →
- Mechanical ContractorUnclaimedClaim this role →
- Electrical ContractorUnclaimedClaim this role →
- Steel FabricatorUnclaimedClaim this role →
- Concrete ContractorUnclaimedClaim this role →
- PlumberUnclaimedClaim this role →
Products used
Drag to scroll