Tihori Solar Farm

Have a better image?

Tihori Solar Farm, first known as the Edgecumbe Solar Farm, is being built on a 209-hectare rural site about 2.5km northeast of Edgecumbe. About 220,000 solar panels will be mounted on single-axis trackers that follow the sun, giving a capacity of 136MWp and about 238GWh of electricity a year. The $236 million project was marked with a sod-turning on 13 March 2026, when construction formally began. A new 33kV line will connect the farm to the Edgecumbe substation. More than 100 construction jobs are expected, and the solar farm is due to be operating by mid-2027 with a design life of at least 35 years.

Timeline

  1. 13 Mar 2026

    A sod-turning was held and construction formally began.

  2. 2027

    The solar farm is expected to be operating by mid-2027.