Te Awaparahi Bay Expansion and Resilience Project

Have a better image?

The Te Awaparahi Bay Expansion and Resilience Project is the largest infrastructure project in Lyttelton Port's history. It adds a 388-metre deepwater wharf and a five-hectare container terminal on reclaimed land at Te Awaparahi Bay, served by four new ship-to-shore cranes and semi-automated yard cranes. The new terminal will take ships of up to 15,000 TEU and lift annual berth capacity to around 850,000 TEU. The port says the Cashin Quay container berths, damaged in the Canterbury earthquakes, may not survive another large quake, and most container ships now being built would not fit the current layout. Dredging of the berth pocket is due to start in late 2026, wharf construction is set to begin in mid-2027, and the project is expected to be finished by 2031.

Timeline

  1. 2026

    Dredging of the berth pocket is due to start in late 2026.

  2. 17 Aug 2026

    Lyttelton Port Company confirmed an $821 million investment in the expansion.

  3. 1 Sep 2026

    An expression of interest for wharf construction was released to the market.

  4. 2027

    Wharf construction is due to start in mid-2027.

  5. 2031

    The project is expected to be complete by 2031.