SH1 Belfast to Pegasus Motorway and Woodend Bypass
The Belfast to Pegasus Motorway and Woodend Bypass extends the four-lane motorway north of Christchurch for about 11km, from south of the Kaiapoi River Bridge to just north of the Pegasus and Ravenswood intersection. It takes State Highway 1 traffic around Woodend, where about 21,500 vehicles a day pass through, and includes a grade-separated interchange at Williams Street and an overpass replacing the Pegasus roundabout. Early work began in 2026 with seismic strengthening of the Kaiapoi River Bridge and the filling of two quarry lakes near Pineacres. The project received fast-track approval in July 2026 and is a Road of National Significance. Main construction is expected from late 2026, with completion targeted for 2030, and tolling has been proposed to help fund it.
Timeline
Nov 2024
The NZTA Board approved initial funding for detailed design and an early works package.
Feb 2026
The NZTA Board approved about $127 million for detailed design, property purchase and early work.
Feb 2026
Early physical work started, including strengthening of the Kaiapoi River Bridge.
Jul 2026
The project was granted fast-track approval.
Dec 2026
Main construction is expected to begin in December 2026, with completion expected in December 2030.
Project team
- Client / DeveloperUnclaimedClaim this role →
- Project ManagerUnclaimedClaim this role →
- Quantity SurveyorUnclaimedClaim this role →
- ArchitectUnclaimedClaim this role →
- Structural EngineerUnclaimedClaim this role →
- Building Services EngineerUnclaimedClaim this role →
- Civil EngineerUnclaimedClaim this role →
- Fire EngineerUnclaimedClaim this role →
Build team
- Main ContractorUnclaimedClaim this role →
- Mechanical ContractorUnclaimedClaim this role →
- Electrical ContractorUnclaimedClaim this role →
- Steel FabricatorUnclaimedClaim this role →
- Concrete ContractorUnclaimedClaim this role →
- PlumberUnclaimedClaim this role →
Products used
Drag to scroll