Queenstown Airport Heavy Taxiway and Runway Upgrade

Have a better image?

The heavy taxiway and runway upgrade is the largest airfield investment in Queenstown Airport's history. A new 1,600-metre Code C taxiway is being built alongside the main runway so landing aircraft can return to the apron, and departing aircraft can reach the runway threshold, without backtracking along the runway. The work also includes a full overlay of the main runway to extend its life. The runway is not being lengthened and no larger aircraft will be introduced. Work started at the Shotover end of the airfield and runs in day and night stages so the airport stays open. The first sod was turned on 14 July 2026, and the airport has targeted completion for mid-2027.

Timeline

  1. 13 May 2026

    The airport confirmed plans for the heavy taxiway, with construction expected to begin in July.

  2. 14 Jul 2026

    The first sod was turned and construction started.

  3. 2027

    Completion is targeted for mid-2027.