Puke Kapo Hau Wind Farm
Puke Kapo Hau is the second stage of the Māhinerangi Wind Farm, about 50km west of Dunedin and north of Lake Māhinerangi. It adds 40 turbines with a combined capacity of 192MW to the wind farm that has run since 2011, along with a new 110kV transmission line and substation, and will make it the largest wind farm in the country once complete. The project was approved through the fast-track process in July 2026, and the go-ahead for the $506 million build was given in October 2026. Preliminary construction was scheduled to begin in November 2026, with the first turbines going up in early 2028. The wind farm is expected to produce about 550GWh a year, and commissioning is planned for 2028.
Timeline
3 Jul 2026
The wind farm was granted fast-track approval.
Oct 2026
An order was placed for 40 turbines totalling 192MW.
15 Oct 2026
Notice to proceed was issued for the $506 million development.
Nov 2026
Preliminary construction was scheduled to begin.
2028
The first turbine is due to be installed in early 2028, with commissioning planned for mid-2028.
Project team
- Client / DeveloperUnclaimedClaim this role →
- Project ManagerUnclaimedClaim this role →
- Quantity SurveyorUnclaimedClaim this role →
- ArchitectUnclaimedClaim this role →
- Structural EngineerUnclaimedClaim this role →
- Building Services EngineerUnclaimedClaim this role →
- Civil EngineerUnclaimedClaim this role →
- Fire EngineerUnclaimedClaim this role →
Build team
- Main ContractorUnclaimedClaim this role →
- Mechanical ContractorUnclaimedClaim this role →
- Electrical ContractorUnclaimedClaim this role →
- Steel FabricatorUnclaimedClaim this role →
- Concrete ContractorUnclaimedClaim this role →
- PlumberUnclaimedClaim this role →
Products used
Drag to scroll