Nelson Hospital New Inpatient Building
The new inpatient building is the main part of the Nelson Hospital redevelopment. The five-storey, 11,000 square metre building will have 128 beds, 41 more than today, along with an acute assessment unit, transit lounge, pharmacy, blood bank and areas for assessment, treatment and rehabilitation. A new energy centre will support the hospital's critical services. The Government confirmed the redevelopment in May 2025 with $73 million for design and enabling works. Enabling works began in 2025 and main construction was expected to start at the end of 2026, with the building due by 2029. The George Manson and Percy Brunette buildings will also be refurbished and strengthened.
Timeline
26 May 2025
The Government confirmed the Nelson Hospital redevelopment, including a 128-bed inpatient building due by 2029.
Sep 2025
Enabling works were under way, with main construction expected to start at the end of 2026.
11 Dec 2025
An external project management team was appointed, with design of the inpatient building and energy centre due to begin in April 2026.
2029
The new inpatient building is due to be finished by 2029.
Project team
- Client / DeveloperUnclaimedClaim this role →
- Project ManagerUnclaimedClaim this role →
- Quantity SurveyorUnclaimedClaim this role →
- ArchitectUnclaimedClaim this role →
- Structural EngineerUnclaimedClaim this role →
- Building Services EngineerUnclaimedClaim this role →
- Civil EngineerUnclaimedClaim this role →
- Fire EngineerUnclaimedClaim this role →
Build team
- Main ContractorUnclaimedClaim this role →
- Mechanical ContractorUnclaimedClaim this role →
- Electrical ContractorUnclaimedClaim this role →
- Steel FabricatorUnclaimedClaim this role →
- Concrete ContractorUnclaimedClaim this role →
- PlumberUnclaimedClaim this role →