Mt Cass Wind Farm is being built on a 7.5km ridge on Mt Cass, about 5km east of Waipara in North Canterbury. Its 22 turbines will have a combined capacity of 94.6MW and are expected to produce more than 300GWh a year, enough for about 40,000 households. The project was first proposed in 2006 and gained consent through the Environment Court in 2011, but stalled for years before it changed hands in December 2025. Main construction began on 6 January 2026 with a site compound, laydown area and access roads to the top of the ridge. The turbines are due to arrive at Timaru Port in mid-2027, and the wind farm is expected to start operating in 2028.

Timeline

  1. Dec 2011

    The Environment Court granted consent for a modified design.

  2. 18 Dec 2025

    The project was sold to a new owner, with construction expected to start in early 2026.

  3. 6 Jan 2026

    Construction started at the site entrance with a compound and laydown area.

  4. 2027

    Turbines are due to arrive at Timaru Port in July or August 2027.

  5. 2028

    The wind farm is expected to start operating in 2028.