Huntly Battery Energy Storage System Stage 2

Have a better image?

The second stage of the Huntly battery adds 100MW of capacity and 200MWh of storage at Huntly Power Station, the country's largest power station. It sits alongside the first-stage battery and brings the site total to 200MW and 400MWh, connected to the grid through the Transpower substation at Huntly. The final investment decision was made in April 2026 on an estimated cost of about $106 million, described as the lowest-cost committed grid-scale battery in New Zealand so far. Construction was expected to begin in the second quarter of the 2027 financial year, with commercial operation targeted for the third quarter of the 2028 financial year.

Timeline

  1. 2026

    Construction is expected to begin in the second quarter of the 2027 financial year.

  2. 17 Apr 2026

    The final investment decision was made on the second-stage battery.

  3. 2028

    Commercial operation is targeted for the third quarter of the 2028 financial year.