Glenbrook Ohurua Battery 2 is a 200MW grid-scale battery on industrial land leased from New Zealand Steel at Glenbrook in South Auckland, next to the first Glenbrook battery. It will store up to 400MWh, enough to supply about 88,000 homes for around two hours at peak times, and about 132,000 homes together with the first battery. The battery is made up of 112 lithium-ion units covering an area about the size of two rugby fields, connected directly to the national grid. Construction began in February 2026 and the battery is expected to be operating in 2028, storing power when it is cheap and plentiful and releasing it during peaks.

Timeline

  1. Feb 2026

    Construction began.

  2. 2028

    The battery is expected to be operating in 2028.