The pastry butter sheet expansion adds a new production line at Fonterra's Edgecumbe dairy site in the eastern Bay of Plenty. Pastry butter sheets are used by bakeries to make laminated products such as croissants and puff pastry, and the line responds to growing demand from China, Mexico and Southeast Asia. The $35 million project will double the site's pastry butter sheet capacity from 10,000 to 20,000 tonnes a year and create four new permanent roles. A dawn blessing in April 2026 marked the start of construction, which is expected to take around 12 months, with the first product due off the line in April 2027.

Timeline

  1. Apr 2026

    A dawn blessing marked the start of construction.

  2. Apr 2027

    The first product is expected to come off the line in April 2027.