Arlington Social Housing Development

Have a better image?

The Arlington development is a Kāinga Ora social housing project on council-owned land in Mount Cook, central Wellington. The revised plan has 104 homes: 55 one-bedroom and 37 two-bedroom apartments in a seven-storey building, plus 12 four-bedroom terrace homes and a community room for residents. An earlier plan for 301 homes was paused in 2023 after its budget rose from $296 million to $419 million. The former housing complex has been demolished and the site prepared, and piled foundations already laid for one building will be reused. The reset was announced in August 2026 and still needs a council lease variation, an approved investment case and consents. If approved, construction is expected to begin in late 2027 and finish in late 2029. The rest of the site will return to the council for other housing.

Timeline

  1. 2019

    Kāinga Ora (then Housing New Zealand) agreed a 125-year lease of the site with Wellington City Council.

  2. Oct 2021

    The Kāinga Ora Board approved plans for 301 homes at a cost of $296 million.

  3. Jul 2023

    The project was paused after costs rose to $419 million.

  4. 13 Aug 2026

    The Government announced a reset to deliver 104 social homes on the site.

  5. 2027

    Construction is expected to begin in late 2027, subject to approvals.

  6. 2029

    Completion is expected in late 2029.