Ara Tūhono Warkworth to Te Hana

Have a better image?

Ara Tūhono Warkworth to Te Hana is the first stage of the Northland Expressway. The new 26km four-lane road runs west of the existing State Highway 1, with grade-separated interchanges at Warkworth, Wellsford and Te Hana. It includes twin tunnels of about one kilometre through Kraack Hill above the Dome Valley, 15 bridges, two underpasses and 12 wetland stormwater basins. The project is being delivered as a public-private partnership, the largest New Zealand has undertaken, with a net present value of $3.649 billion. It is expected to cut 7 to 10 minutes from travel times, reduce weather closures and take about 1,000 heavy vehicles a day off the route through Wellsford. Early works start from late 2026, main construction from November 2027, and the road is due to open in 2033.

Timeline

  1. 2026

    Detailed design, site mobilisation and early works were due to begin in the months after financial close.

  2. 30 Jul 2026

    The public-private partnership agreement was signed and the project reached financial close.

  3. Nov 2027

    Main construction is scheduled to start in November 2027.

  4. 2033

    The road is expected to open in 2033, with full completion in 2034.